Moisture Management: Walls

Panels should be kept in storage or under cover until installed. Product on the job site should be covered and well off the ground. After installation, cover with house wrap as soon as possible.

Panel Storage

1. Build platform of cull panel and scrap lumber 4x4s for stacking panels.

Stretch plastic film over platform to block passage of ground moisture.

Moisture Management Step 1

2. Nail film to top panel and drape over ends for protection against driving rain.

Weight lower end with 2×4.


Moisture Management Step 2

3. Lay two 2x4s on top of stack.

Pad corners with rags.

Stretch film over stack and secure to tie-down stakes.

Moisture Management Step 3